Signal Too Low. Permanent Fault
Checking for a Short-circuit
- Check cable between canister purge (CP) valve terminal 2 and engine control module (ECM) # A39 for a short-circuit to ground.
- Proceed to: Verification section below.
Verification
After carrying out the repair, check that the fault has been remedied as follows:
- Ignition OFF.
- Canister purge valve and control module connected.
- Ignition ON.
- Activate canister purge valve.
- A "clicking sound" can be heard from the canister purge valve when it is activated.
- Is the canister purge valve working?
If reading is OK:
^ Fault corrected.
If reading is incorrect:
^ Proceed to: Fault-tracing Information section below.
Fault-tracing Information
The verification result shows that the fault persists.
- Do you want to exit fault-tracing?
Yes:
^ Fault not corrected.
No:
^ Proceed to: Checking for a Short-circuit section above.