Installation
2GR-FE ENGINE CONTROL: VACUUM SWITCHING VALVE (for Engine Mounting): INSTALLATION
1. INSTALL DUTY VACUUM SWITCHING VALVE
(a) Connect the hose to the duty vacuum switching valve and install the duty vacuum switching valve with the bolt.
Torque : 4.0 Nm (41 kgf-cm, 35 in-lbf)
(b) Connect the 3 vacuum hoses to the duty vacuum switching valve.
HINT
* Hose A: Large hose
* Hose B: Dummy hose (not used for ventilation, the other end is plugged)
(c) Connect the duty vacuum switching valve connector and clamp.
2. INSTALL NO. 1 AIR CLEANER INLET Installation
3. INSTALL BATTERY Installation
4. INSTALL NO. 2 AIR CLEANER INLET Installation
5. INSTALL V-BANK COVER SUB-ASSEMBLY Installation
6. INSTALL COOL AIR INTAKE DUCT SEAL Installation
7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.
8. INSTALL NO. 2 ENGINE UNDER COVER
9. INSTALL NO. 1 ENGINE UNDER COVER