1. INSTALL GENERATOR ASSEMBLY
(a) Install the wire harness clamp with the bolt.
Torque : 8.4 Nm (86 kgf-cm, 74 in-lbf)
(b) Install the 2 bolts.
Torque : 43 Nm (438 kgf-cm, 32 ft-lbf)
(c) Install the generator bracket with the 2 bolts.
Torque : 20 Nm (204 kgf-cm, 15 ft-lbf)
(d) Connect the wire harness clamp.
(e) Connect the generator connector to the generator assembly.
(f) Install the generator wire with the nut.
Torque : 9.8 Nm (100 kgf-cm, 87 in-lbf)
(g) Install the terminal cap.
(h) Connect the 2 wire harness clamps.
(i) Connect the magnetic clutch connector to the compressor and magnetic clutch.
2. INSTALL V-RIBBED BELT
HINT
Installation
3. INSTALL RADIATOR ASSEMBLY
HINT
Installation
4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.