Installation
E351 MANUAL TRANSAXLE: FLOOR SHIFT CABLE TRANSMISSION CONTROL SHIFT:
INSTALLATION
1. INSTALL FLOOR SHIFT CABLE TRANSMISSION CONTROL SHIFT
(a) Thread the shift cable through the floor hole and retainer.
(b) Connect the select cable to the grommet.
(c) Install the retainer to the grommet.
NOTE: Fit the 3 projections of the grommet into the 3 holes of the retainer.
(d) Install the 2 retainer set bolts.
Torque: 5.0 Nm (51 kgf-cm, 44 in-lbf)
(e) Connect the shift cable to the shift lever retainer.
- The projecting part of the cable outer should face upward when the shift cable is connected.
- After installation, make sure that the cable outer lock is projecting from A as shown in the illustration.
(f) Install the top end of the shift cable to the shift lever assembly.
(g) Connect the shift cable to the control cable bracket and install a new clip.
(h) Connect the shift cable to the transaxle and install the washer and clip.
2. INSTALL AIR BAG SENSOR ASSEMBLY CENTER
HINT: (Installation)
3. REMOVE AIR CONDITIONING RADIATOR ASSEMBLY
HINT: (Installation)
4. REMOVE INSTRUMENT PANEL SAFETY PAD SUB-ASSEMBLY W/PASSENGER AIR BAG ASSEMBLY
HINT: (Installation)