Secondary Control Valve Body Installation
SECONDARY CONTROL VALVE BODY INSTALLATION [FS5A-EL]On-Vehicle Installation
1. Install the tubular pin and new O-ring to the transaxle case.
2. Install the secondary control valve body component and ground.
Tightening torque 7.8 - 10.8 N-m (80 - 110 kgf-cm, 70 - 95 in-lbf)
Bolt length (measured from below the head)
B: 40 mm (1.575 in)
C: 50 mm (1.967 in)
3. Match the harness colors, then connect the solenoid connector.
4. Apply a light coat of silicon sealant to the contact surfaces of the oil cover and transaxle case.
5. Install the oil cover.
Tightening torque 7.8 - 10.8 N-m (80 - 109 kgf-cm, 70 - 95 in-lbf)
6. Install the bracket in the figure.
Tightening torque 18 - 26 N-m (1.9 - 2.6 kgf-m, 14 - 19 ft-lbf)
7. Install the battery and battery tray.
8. Connect the negative battery cable.
9. Add ATF.
10. Carry out the mechanical system test. (See MECHANICAL SYSTEM TEST [FS5A-EL].) Mechanical System Test
11. Carry out the road test. (See ROAD TEST [FS5A-EL].) Road Test