| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
| Replace |
| Add Following Operations If Performed With Piston & Ring Jobs |
| Main Bearings, Renew | 4.3 | 0.0 | A | |
| Crankshaft, Renew | 4.7 | 0.0 | A | Does Not Include: R&R Engine. |
| Oil Pump, Renew | 1.5 | 0.0 | A | |
| Oil Pump Screen, Clean | 0.2 | 0.0 | A | |
| Rear Main Seal, Renew | 0.3 | 0.0 | A | After Engine Or Trans Are Removed. |
| Timing Chain, Renew | 3.2 | 0.0 | A | |
| Tune-Up | 0.6 | 0.0 | A | |
| Valves, Grind |
| See Valves, Grind Head Removed And Combinations. |
| One Cylinder | 12.7 | 9.3 | A | Includes: R&R Cylinder Head & Oil Pan, Hone Cylinders And Plastigage Bearings. |
| One Cylinder Each Bank | 14.7 | 10.8 | A | Includes: R&R Cylinder Head & Oil Pan, Hone Cylinders And Plastigage Bearings. |
| All Cylinders | 21.3 | 15.0 | A | Includes: R&R Cylinder Head & Oil Pan, Hone Cylinders And Plastigage Bearings. |