| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
| Replace |
| Add Following Operations If Performed With Piston & Ring Jobs |
| Main Bearings, Renew | 0.9 | 0.0 | A | |
| Crankshaft, Renew | 4.2 | 0.0 | A | Includes: R&R Engine |
| Oil Pump, Renew | 0.9 | 0.0 | A | |
| Timing Gears, Renew | 2.4 | 0.0 | A | |
| Tune-Up | 0.5 | 0.0 | A | |
| Valves, Grind |
| See Valves Grind (Head Removed) And Combinations. |
| One Cylinder | 8.0 | 5.7 | A | Includes: R&R Cylinder Head And Oil Pan. |
| Note |
| With AC, Add | 0.7 | 0.4 | A | |
| With Cruise Control, Add | 0.2 | 0.1 | A | |
| All Cylinders | 10.1 | 7.0 | A | |
| Note |
| With AC, Add | 0.7 | 0.4 | A | |
| With Cruise Control, Add | 0.2 | 0.1 | A | |